Statistical Data
 
Rural Electrification

Total Nos. of villages in Jharkhand        

32615

:

32615

Nos. of inhabited villages  

29445

:

29445

 

Electrification Work from 2001-02 to 2007-08

(A) Nos. of Villages Electrified after creation of Jharkhand

2001-02

537

:-

537

2002-03

771

:-

771

2003-04

1225

:-

1225

2004-05

1113

:-

1113

485

:-

485


Rites

2005-06

702

:-

702

723

238

:-

238

Rites

2006-07

324

:-

324

2007-08

179

:-

179

Total (A)

5574

:-

5574

(B) Nos. of villages electrified before creation of Jharkhand (B)                                                             :          3859

:-

3859

Note:- As per available data in RE.

( C ) RGGVY :-

Agency

Physical Achievement of Villages

BPL

P/S/S Status

Agency

Tgt after Survey

 Achievement

Energised

 

Ach

Energised

Target

Ach

Energised

JSEB

4650

3787

3763

 

336704

315406

33

22

22

DVC

5234

5015

4181

 

416732

366723

42

34

32

NTPC

8904

8642

8642

 

548187

432076

32

29

25

Total

18788

17444

16586

 

1301623

1114205

107

85

79

Note:- As per report furnished by DVC & NTPC. Reports under JSEB is under TPIA verification.

Total Completed Villages in RGGVY

:-

17444

Total Energised villages in RGGVY (C)

:-

16586

Balance to be energised in RGGVY

:-

858

Total Energised villages in Jharkhand state (A+B+C)                                          26019

:-

26019

% energised wrt total 32615 :-

79.8%

% energised wrt total 29445 :-

88.4%

Total completed villages in Jharkahand electrified uptill now      30.09.13         26877

30.09.13

:-

26877

Balance No. of Villages to be electrified uptill now     (29445-26877) = 2568

 

 

 

)            :-

2568

 Balance in RGGVY -

-1095417

  Rest others :-

1097985

Not energised + to be electrified        (29445-26019)  = 3426

 

 

26019

)            :-

3426

 

 

 

Rural Electrification
 
Status of RGGVY in Jharkhand State

 

JSEB:-

  • Revised target of JSEB is now 4650 (UE) villages out of which 3787 completed. (This is because reduction in target and achievement of Saraikela dist as reported earliear)
  • Out of total 863 UE+DE and 301 PE villages under JSEB, to be electrified under RGGVY  programme, in Kolhan Division (Singhbhum(W) and Saraikela Districts) balance to be completed is  262 UE+DE villages and 27 PE villages.
  • Also in Kolhan division out of 14 nos. 33/11 kV PSS, 09 numbers of PSS have been completed, balance 05 numbers of 33/11 kV PSS is to be completed. 3 nos. P/S/S is under Singhbhum(W) (namely Bandgaon,Tonto and Tantnagar) and 2 nos. P/S/S is under Saraikela districts (namely Ichagarh and Nimdih). Revised cost of estimate has been received from REC recently.  Work likely to be completed by March’14.
  • In three packages of Palamau division (Latehar, Garhwa and Palamau dist.) balance villages to be done are 601 UE+DE villages and 274 PE villages. Out of 19 nos.  33/11 kV PSS, 13 numbers of PSS have been completed, balance 06 numbers of 33/11 kV PSS is to be completed ( 2 nos in Latehar and 4 nos in Garhwa). M/s IVRCL has discontinued execution of the work.
  • The fore-closure of the scheme of Latehar Garhwa and Palamau district will be required as the agency is reluctant to carry on the job further. For foreclosure of the scheme under RGGVY in Latehar, Garhwa and Palamau districts proposal likely to be finalized at the earliest. Subsequently the DPR have to be prepared for getting the work executed under 12th plan. Consultant for preparation of DPR has also been engaged.
  • Out of 554768 BPLs 336704 BPL connection released and 315406 energised. Out of balance 218064 BPLs 53007 BPL are under Singhbhum(W) and Saraikela- Kharsawan District and rest 16,1196 falls under Latehar Garhwa and Palamau districts.

DVC :-     

  • The balance villages to be completed by DVC is 219 UE+DE and 78 PE  villages. These are in Chatra -283 (205 UE and 78 PE) villages, Simdega- 2 villages and Gumla – 12 villages.
  • 834 UE villages are to be energized. Gumla- 10, Simdega- 112, Chatra- 690 Hazaribagh -7 and Girdih- 15.
  • 137 PE villages are to be energized. Simdega- 7, Chatra- 126, Hazaribagh- 1 and Girdih – 10.
  • DVC balance no. of 33/11 Kv P/S/S to be completed is 8 in Chatra (namely Pratappur, Tandwa, Gidhaur, Simaria, Pathalgora, Kunda, Hunterganj & Lawalong) and 2 completed P/S/S in Simdega District ( namely Kurdeg and Bolba ) is to be energized. REC has accorded special sanction for construction of 33 KV line which will take care of feeding power to P/S/S situated in the district to facilitate energization of villages. PSS affected by no grid connectivity. Construction of additional 33 KV line has been taken up to resolve connectivity problem in which forest clearance involved. PSS shall be completed and charged within 3 months of getting forest clearance.    
  • P/S/S target and BPL target will be completed along with completion of village target.
  • Out of 20 Forest Clearance proposals of DVC, Stage-I clearance obtained for 18. Pending 1 No. at PCCF cum ED Ranchi-I, 1 No. Clearance given by DFO Gumla on 22.08.13.
  • For additional 33 KV line proposals for Chatra, Girdih and Simdega district ,stage –I clearance given for Chatra- 14, Girdih- 3 and Simdega -1.
  • In Hazaribagh District in Chouparan block under wild life sanctuary. Underground cabling is decided for which RCE has been submitted.

NTPC/NESCL :-     

  • The balance villages to be completed by NTPC is 262 UE+DE and 125 PE villages. These are in Ranchi -320 (255 UE and 65 PE) villages, Godda – 65 (7 UE and 58 PE) villages and Sahebganj 2 PE villages..
  •  NESCL balance no. of 33/11 Kv P/S/S to be completed in Ranchi is 3 (namely Rania, Mander and Erki) and completed but to be energized is 4 no.s( namely Lapung, Burmu, Murhu and Tamar).
  • P/S/S target and BPL target will be completed along with completion of village target.
  • NTPC/ NESCL is facing problem in Ranchi district mainly due to law and order problem and ROW problem. Due to law and order problem agency states that PSS at Erki and 33 KV line in Murhu to Erki cannot be completed. However JSEB ensures full co-operation for completion.
  • Kanke GSS is completed by JSEB. Kanke to Burmu and kanke to Mandar 33 KV line is yet to be completed by NTPC. Tentative date of completion is Dec’13 and Jan’14 respectively.

Rural Franchisee
Jharkhand state electricity Board as per RGGVY guidelines has deployed successfully rural franchisee in 11 subdivisions in first stage and 6 sub-divisions 2nd stage till date. In third stage 15 more NIT floated out of which 13 opened and under examination, likely to be awarded by 13.10.13. Rest 2  (Chaibasa Rural & Rajkharsawan )extended due to insufficient applicant. Again only two applicants received for Chaibasa Rural which will be opened after getting permission at competent level. And for Rajkharsawan sub division process of retendering is underway as no application received.
Constraints in Completion of RGGVY

  • Work is likely to be completed by Mar’14, RCE of Singhbhum(W) and Saraikela Kharsawan Districts has been just approved.
  • stopped the work in above districts and initiated case against JSEB due to which 601 UE+DE villages, 274 Nos. of PE (PE) villages, 06 nos. of P/S/S and 161196  BPLs are not completed. To be covered in 12th plan.
  • Reimbursement of amount deducted on account of infrastructure used in de-electrified villages in RCE of Singhbhum West & Saraikela-Kharsawan.(Forwarded to Energy Dept. & REC, Ranchi Vide letter no- 602/RE dated-26.09.13.)

                                       

Status of DPR preparation under RGGVY 12th plan.
There is 24 districts in Jharkhand State. Under 12th plan of RGGVY for preparation of DPR, JSEB has allotted work to consultants namely M/s RECPDCL,M/s MECON and M/s AKS in 11,8 & 5 district respectively. In 12th plan of RGGVY the electrification is to be covered in leftover villages/Tolas of 10th & 11th plan of RGGVY, whose population is more than 100 & every house, common places is to be electrified. Village wise survey of agencies is under progress.
Replacement of Burnt Transformer under RGGVY
Total Numbers of transformers installed under RGGVY is about = 46799 
Status of burnt transformers as per report by field officers = 3754 Nos. (as on Sept’13)
Burnt transformers replaced with 25 KVA of Transformers = 1590 Nos. (up to Sept’13)
Additional 25 KVA of Transformers installed = 107 Nos. (up to Sept’13)                                       
Balance to be replaced = 2164 Nos. ( By Oct’13) 
Departmental electrification of 1291 villages/tolas(not covered in any scheme and RITES left over)

Jharkhand state electricity Board is taking up electrification of 1291 villages/tolas (not covered in any scheme & departmental left over ( 463 & 301) and RITES left over (74 virgin & 453 partial). Procurement of material and work has been started. Presently  there is progress in 107 villages. Project is likely to be completed by end of March’14. 

 
 
 
 
 
 
 
Official Mail Login   |   Events   |    Gallary   |     Feedback |    Enquiry  |    Contact Us
         
Home | Contact Us | Privacy Policy | Disclaimer | Site Map
© Copyright Jharkhand Urja Vikash Nigam Ltd. 2015. This site belongs to JUVNL Last Updated : 23/01/2014